MTA falls further behind on $2B in upgrades to NYC subway signals, consultant finds


By

Ramsey Khalifeh

Published Nov 16, 2026 at 3:56 p.m. ET


Share

FacebookTwitterRedditEmail


Never miss a story

 Email address

By submitting your information, you're agreeing to receive communications from New York Public Radio in accordance with our Terms .

The MTA is working to upgrade subway signals that guide trains on some of the city's busiest lines.

 

MTA / Trent Reeves


By

Ramsey Khalifeh

Published Nov 16, 2026 at 3:56 p.m. ET


Share

FacebookTwitterRedditEmail


We rely on your support to make local news available to all

Make your contribution now and help Gothamist thrive in 2026. Donate today

Gothamist is funded by sponsors and member donations

The MTA has fallen further behind schedule on a massive effort to upgrade aging signal technology that guides trains on some of the city’s busiest subway lines, according to a report published Monday by a consultant for the transit agency.

The signals will replace 1930s-era technology with new systems designed to allow trains to run faster and closer together. The agency’s consultant last year found the signal upgrades had faced months of delays, and the new report found that unanticipated infrastructure repairs and software issues have pushed the installation back even more.

The report stated the upgrades to signals on the A, C and E lines running along Eighth Avenue were running 15 months behind schedule and wouldn’t be completed until January 2029. The consultant reported another eight months of delays in the project to add new signals on the F and E lines in eastern Queens, which is also expected to wrap in January 2029. And the effort to upgrade the signals on the G line, which has caused regular service disruptions for riders, is delayed another 14 months and a final determination for a complete date is still being considered, the report found.

The consultant noted the new signal technology was expected to be operational months before each project wraps. The construction timelines published in the report also include other technical work.

MTA officials last year blamed delays in signal upgrades on contractors the agency hired and a lack of engineering expertise in the field of signal work. The agency earlier this year said the delays in the G line work were in part due to leaks that workers found in the Greenpoint Tube under Newtown Creek, which took a year to repair.

MTA construction chief Jamie Torres-Springer said Monday that riders were already seeing benefits from the disruptions to G train service, noting the agency has added new elevators and modern subway cars to the line.

“I just want to be clear that as we’re doing this work, the benefits to riders accrue incrementally even before we get to turning on the CBTC program and it’s a good new story in that way,” Torres-Springer said.

He said the delays to the Eighth Avenue project were “primarily due to software issues” and the "unavailability" of time to test the technology on subway tracks.

Dr. Nabil Ghaly, a signal technology expert who issued the report for the MTA consultant at the agency’s committee meeting, said it was difficult to upgrade New York City’s subway signals because the system runs around the clock.

“The [independent engineering consultant] recognizes that implementing [communications-based train control] on an existing transit system that operates 24/7 presents operational, technical and physical complexities,” Ghaly said.

The consultant estimated the combined cost of the three delayed signal projects at more than $2 billion. The MTA earlier this month also started work on another $2 billion project to upgrade the signals on the Fulton-Liberty line, where the A and C trains run in Brooklyn and Queens.

Modern signals are already operational on the entire lengths of the L and 7 lines. The MTA also completed an upgrade to the signals on the F line in Brooklyn last year.

Officials said they plan to release a new report on Wednesday that lays out the MTA’s vision of implementing the new signal technology on every subway line.

Tagged

brooklyn

manhattan

new york city

queens

transportation


Ramsey Khalifeh

Ramsey Khalifeh is a transportation reporter on the NYC Accountability desk covering the largest transit system in the country. He was previously a general assignment reporter at Gothamist and worked on the Boston Globe's metro and copy desk. Got a tip? Email [email protected]

Read more

Gothamist is funded by sponsors and member donations


Gothamist is funded by sponsors and member donations


MORE news

MTA will test body-worn cameras on bus fare enforcement teams

The move comes after members of the EAGLE team were caught on video tackling a rider suspected of not paying the fare.

By

Stephen Nessen

Published Nov 16, 2026 at 3:52 p.m. ET


Chase, Bank of America and other major banks report online banking outages

Customers reported trouble accessing accounts and completing transactions on Monday. Chase says a technical issue is to blame.

By

Giulia Heyward

News

Chase, Bank of America and other major banks report online banking outages

Customers reported trouble accessing accounts and completing transactions on Monday. Chase says a technical issue is to blame.

By

Giulia Heyward


2 Co-op City peace officers shot during Bronx wellness check, officials say

By

Charles Lane

NY, the 'Freedom Summer' murders and an improbable election win in Mississippi

By

Amanda Rozon

Early Addition: There are bigger flukes than winning the NYC affordable housing lottery

By

James Ramsay


Never miss a story

Catch up on the most important headlines with a roundup of essential NYC stories, delivered to your inbox daily.

Sign upEmail address

By submitting your information, you're agreeing to receive communications from New York Public Radio in accordance with our Terms .