Buckled beams sit below major expansion of Midtown Pfizer conversion project, officials say


By

David Brand

Published Jul 7, 2026

Modified Jul 7, 2026


Share

FacebookTwitterRedditEmail


Never miss a story

 Email address

By submitting your information, you're agreeing to receive communications from New York Public Radio in accordance with our Terms .

FDNY drone images show damage inside the Midtown construction site where officials say structural columns buckled, prompting evacuations and fears of a localized collapse.

 

Courtesy of FDNY.


By

David Brand

Published Jul 7, 2026

Modified Jul 7, 2026


Share

FacebookTwitterRedditEmail


We rely on your support to make local news available to all

Make your contribution now and help Gothamist thrive in 2026. Donate today

Gothamist is funded by sponsors and member donations

New York City officials revealed new details Tuesday about the structural failure at Manhattan's largest office-to-residential conversion project, saying buckled structural columns were located directly beneath a 10-story expansion designed to widen the building's upper floors.

Photos released by the FDNY on Tuesday show a severely bent column on the 21st floor of the building at 235 East 42nd St. One photo appears to show the addition sagging from the side of the building. The damage is directly below a horizontal expansion spanning floors 23 through 32 that adds square footage to the former Pfizer headquarters.

Department of Buildings spokesperson David Maggiotto described the expansion as a "horizontal bump-out."

"For floors 23-32, the building is undergoing a horizontal bump-out to widen the structure at these floors," Maggiotto said. "The building has a tiered 'wedding cake' structure and is wider at the base than at the highest point."

The project also includes plans to add four new floors to the top of the building, which is being converted into roughly 1,600 apartments.

A 2024 zoning document depicting the project includes the planned four-story rooftop addition but does not depict the horizontal bump-out.

Maggiotto said investigators have not determined what caused the structural failure, and cautioned against drawing conclusions about whether the expansion played any role.

By Tuesday evening, Department of Buildings officials said engineers had completed an initial assessment, found no additional movement in the damaged columns and cleared contractors to begin installing temporary shoring. Officials said the stabilization work was expected to continue through the evening and into the coming days.

Officials also started allowing some nearby residents to return home while continuing to evaluate other evacuated buildings.

Fire officials said two structural columns buckled on the 21st floor, causing floors above to sag. The building was evacuated Tuesday morning after officials determined it was unstable. Engineers spent the day monitoring movement inside the structure.

By late afternoon, officials said they had detected no additional movement in the damaged columns and authorized contractors to begin installing temporary shoring.

Gensler, the architecture firm that designed the project, declined to comment and referred questions to the developer, MetroLoft.

In a written statement, MetroLoft Senior Managing Director Mitchell Wasser said the “safety of everyone at and surrounding the building is our number one priority.”

“We want to confirm that the affected area is a small section of one of the two buildings on this site,” Wasser said.

This is a developing story and has been updated with new details.

Tagged

manhattan


David Brand

David is a reporter covering housing for Gothamist and WNYC. Got a tip? Email [email protected] or Signal 908-310-3960.

Read more

Gothamist is funded by sponsors and member donations


Gothamist is funded by sponsors and member donations


MORE news

Federal judge dismisses Trump administration lawsuit over New Jersey voter rolls

The ruling rejects the Justice Department’s effort to force New Jersey to provide voter registration records.

By

Giulia Heyward

Published Jul 29, 2026 at 6:56 p.m. ET


Confusion reigns over eligibility for Mayor Mamdani’s pied-à-terre tax

“Why are we being targeted?” one Staten Island resident asked.

By

Walter Wuthmann

and

Brigid Bergin

News

Confusion reigns over eligibility for Mayor Mamdani’s pied-à-terre tax

“Why are we being targeted?” one Staten Island resident asked.

By

Walter Wuthmann

and

Brigid Bergin


MTA settles suit to make subway elevators more reliable

By

Ramsey Khalifeh

What does it take to get NYC buildings to test for disease-causing Legionella?

By

Caroline Lewis

Decade-plus push to put floating pool on East River faces another delay

By

Liam Quigley


Never miss a story

Catch up on the most important headlines with a roundup of essential NYC stories, delivered to your inbox daily.

Sign upEmail address

By submitting your information, you're agreeing to receive communications from New York Public Radio in accordance with our Terms .