Amtrak's East River tunnels are in such bad shape that parts crumble at the slightest touch


By

Stephen Nessen

Published May 16, 2025


Share

FacebookTwitterRedditEmail


Never miss a story

 Email address

By submitting your information, you're agreeing to receive communications from New York Public Radio in accordance with our Terms .

An Amtrak official pointing at a tunnel wall.

 

Stephen Nessen


By

Stephen Nessen

Published May 16, 2025


Share

FacebookTwitterRedditEmail


We rely on your support to make local news available to all

Make your contribution now and help Gothamist thrive in 2026. Donate today

Gothamist is funded by sponsors and member donations

To illustrate the major repairs needed in one of Amtrak’s East River tunnels, a top railroad official only needed to brush his hands along a piece of metal.

“This is 130-year-old steel,” Amtrak Project Manager David Cooper told reporters standing on a flatbed work train. “We need to repair this.”

Rusty debris fell to the tunnel floor at the slightest touch. Cooper stood on an uneven slab of concrete beside the tracks that was also crumbling.

“This is something that is not happening quickly. We need to get in properly, repair all these rivets, repair all the steel, apply a proper epoxy coating to stop this corrosion in its path,” he said.

The overnight tour for reporters that went into early Thursday morning came amid an ongoing feud between the MTA and Amtrak over how to repair two East River tunnels damaged by Superstorm Sandy.

Sections of an East River tunnel owned by Amtrak showed signs of serious water damage.

Stephen Nessen

The MTA fears Amtrak’s plan to fully close the tunnels one at a time over three years raises the likelihood of delays for riders on the Long Island Rail Road, which also uses two other East River tunnels for service in and out of Penn Station.

If the repairs encounter any complications, it could create a ripple effect of delays affecting the LIRR, Amtrak and NJ Transit, according to MTA officials. They say Amtrak should repair the tunnels only on nights and weekends.

Cooper insisted that alternative proposal is not feasible. He pointed reporters to a color-coded punch list of 254 East River tunnel repairs in an office near Sunnyside Yards. The work, which Amtrak officials expect to begin as soon as next Friday, will cost $1.6 billion.

The repairs will include plugging cracks in the tunnel's roof, which produced a steady drip of water. One worker jokingly compared the unnerving leak to the Splash Mountain ride at Disney World.

Amtrak says work in the tunnels could begin as soon as next Friday.

Stephen Nessen

Other sections of the tunnel were pocked with holes where water had corroded large chunks of concrete.

Amtrak said workers will frequently go through the tunnel, tapping worrying patches of concrete with a hammer. If the patch makes a hollow sound, they know it needs to be shored up. But those short-term fixes aren’t permanent solutions.

Amtrak argues that a full tunnel closure will allow it to get more work done each day. The railroad plans to fully replace the bench wall and the tracks as well as upgrade electrical cables and the overhead catenary system to last another 100 years.

Water dripped from cracks in the tunnel.

Stephen Nessen

“ Having that 13 months outage provides much more reliability and certainty around the work that needs to be done day to day,” said Amtrak Assistant Vice President Derick Hallahan.

The MTA, Gov. Kathy Hochul, Mayor Eric Adams and Hudson Valley Rep. Mike Lawler continue to argue in favor of limiting closures to nights and weekends.

LIRR President Rob Free said Thursday he could not "stand by and allow our operation to be put in jeopardy to the extent it will be" by Amtrak's project.

When asked what incentive Amtrak has to scrap its plan at the 11th hour, Free said, “its reputation.”

But Amtrak officials were confident the plan will work.

“ We have looked at alternatives and none of them give us the solution that we want, which is 100 years of useful life from the system,” said Youssef Dehne, senior project director at Amtrak.

Tagged

manhattan

amtrak

east river

queens

transportation


Stephen Nessen

Twitter

Stephen Nessen covers transportation. Since 2008 he has reported on everything from Occupy Wall Street, the rebuilding of the World Trade Center site, Hurricane Sandy, to Trump’s campaign for president. His transportation reporting has taken him everywhere from the MTA’s secret Rail Control Center to the gleaming subways of Seoul. Got a tip? Email [email protected].

Read more

Gothamist is funded by sponsors and member donations


Gothamist is funded by sponsors and member donations


MORE news

Central Park birders, others remember 63-year-old woman killed in park

People who said they knew her described her as an artist and a familiar presence in the Ramble.

By

Charles Lane

Published Sep 28, 2026 at 7:04 p.m. ET


Dump truck driver hits and kills cyclist on 34th Street in Midtown, NYPD says

It's the latest in a string of hit-and-run deaths in the city in recent months.

By

Liam Quigley

News

Dump truck driver hits and kills cyclist on 34th Street in Midtown, NYPD says

It's the latest in a string of hit-and-run deaths in the city in recent months.

By

Liam Quigley


New ingredient mandated for Latin American kitchen, restaurant plates in NJ

By

Arya Sundaram

A Brooklyn jail cell filled with smoke. The emergency button failed, a lawyer said.

By

Samantha Max

Crews launch tunnel machines to dig first new Hudson River rail tunnels since 1910

By

Michael Sol Warren


Never miss a story

Catch up on the most important headlines with a roundup of essential NYC stories, delivered to your inbox daily.

Sign upEmail address

By submitting your information, you're agreeing to receive communications from New York Public Radio in accordance with our Terms .